Title: The linkage to the Strategic Plan is subsection 7.2 - Improve competitiveness through infrastructure improvements impacting the quality of life. Award Summary: The award of Solicitation 2022-0306 Ted Houghton Street Reconstruction to ALLEN CONCRETE, LLC for a total estimated award of $1,308,459.64. The project consists of reconstructing Ted Houghton Drive from Double Jay Drive to Rancho Trail Drive to include the removal and disposal of the existing roadway section and placing new curb & gutter, sidewalks, driveways, sidewalk ramps, asphalt concrete pavement, base course, mill and overlay a short roadway segment, placing an underground drainage system, drainage wells, removal and replacement of unsuitable subgrade material, remediation of any structurally deficient retaining walls, street lighting, signing, SWPPP, traffic control and all miscellaneous construction required to complete the work. Department: Capital Improvement Award to: ALLEN CONCRETE...
Attachments: 1. SOLICITATION 2022-0306 TED HOUGHTON STREET, 2. ITEM 46
CITY OF EL PASO, TEXAS
LEGISTAR AGENDA ITEM SUMMARY FORM


DISTRICT, DEPARTMENT, CONTACT INFORMATION:
Please choose District and Department from drop down menu. Please post exactly as example below.
No Title's, No emails. Please use ARIAL 10 Font.
Details
District 6
Capital Improvement Department, Sam Rodriguez, (915) 212-0065
Purchasing and Strategic Sourcing, Claudia A. Garcia, (915) 212-0043
End


AGENDA LANGUAGE:
This is the language that will be posted to the agenda. Please use ARIAL 11 Font.
Title
The linkage to the Strategic Plan is subsection 7.2 - Improve competitiveness through infrastructure improvements impacting the quality of life.

Award Summary:

The award of Solicitation 2022-0306 Ted Houghton Street Reconstruction to ALLEN CONCRETE, LLC for a total estimated award of $1,308,459.64. The project consists of reconstructing Ted Houghton Drive from Double Jay Drive to Rancho Trail Drive to include the removal and disposal of the existing roadway section and placing new curb & gutter, sidewalks, driveways, sidewalk ramps, asphalt concrete pavement, base course, mill and overlay a short roadway segment, placing an underground drainage system, drainage wells, removal and replacement of unsuitable subgrade material, remediation of any structurally deficient retaining walls, street lighting, signing, SWPPP, traffic control and all miscellaneous construction required to complete the work.

Department: Capital Improvement
Award to: ALLEN CONCRETE, LLC
El Paso, TX
Item(s): Base Bid
Initial Term: 300 Consecutive Calendar Days
Base Bid I: $1,308,459.64
Total Estimated Award: $1,308,459.64
Funding Source: 2018 Certificates of Obligation
Account: 190-4743-28900-580270-PCP18ST013
District(s): 6

This is a Low Bid procurement, unit price contract.