All Districts
Purchasing and Strategic Sourcing, K. Nicole Cote, (915) 212-1092
Capital Improvement Department, Yvette Hernandez, (915) 212-0065
End
AGENDA LANGUAGE:
This is the language that will be posted to the agenda. Please use ARIAL 11 Font.
Title
The linkage to the Strategic Plan is subsection: 7.4 Continue the strategic investment in City facilities and technology.
Award Summary:
Discussion and action on the award of Solicitation 2024-0539 Greater El Paso Landfill Cells 15-20 to 4X Construction Group, LLC for a total estimated amount of $17,457,109.29. This project consists of the construction of Greater El Paso Landfill Cells 15-20 that will enhance waste disposal capacity for the City of El Paso.
Department: Capital Improvement
Award to: 4X Construction Group, LLC
City & State: Mansfield, TX
Item(s): Base Bid I and Additive Alternate
Contract Term: 450 Consecutive Calendar Days/Working Days
Base Bid I: $16,780,109.29
Additive Alternate: $677,000.00
Total Estimated Award: $17,457,109.29
Account(s): 334-3150-34130-580270-PESD00240
Funding Source(s): Environmental Services Capital Fund
Districts: All
This was a Low Bid Procurement - unit price contract.
The Purchasing & Strategic Sourcing and Capital Improvement Departments recommend award as indicated to 4X Construction Group, LLC the lowest responsive and responsible bidder.
It is requested that the City Manager be authorized to establish the funding sources and make any necessary budget transfers to execute any and all documents necessary for execution of this award.
Work under this unit price contract is only an estimated value and will be ordered, performed, invoiced, and paid by measured quantity. The actual cost of this contract may be higher or lower than the total estimated value and will be the sum total of unit prices at the end of the contract term.
As part of this award, upon the review of the City Attorney, the City Engineer may without further authorization from City Council approve contract changes which are necessary for proper execution of the work and carrying out the intent of the project, which are in accordance with applicable law, do not make changes to the prices and are within the appropriate budget.